Notes
29,303 application(s) were included for the generation of this chart.
1428 application(s) were filtered out for not having reached Reservation Request Review status.
1,949 application(s) were filtered out for being Cancelled, Withdrawn or Removed.
36 application(s) were excluded for other reasons.
|
 |
Description
The CSI program has a planned phase-down of PBI to 30kW systems by 2010. In 2007, the PBI incentive was required for all systems over 100 kW; in 2008 the PBI incentive was required for all systems of 50 kW; and in 2010 it will be required for all systems over 30kW. However, smaller systems have the option to take the PBI incentive. This chart tracks the number of smaller systems that choose this option over the EPBB incentive in 2008.
Application Data
Working Data Set 
Download Raw Source Data
Excluded Applications 
|